Quantities for unit volume.


Quantities for unit volume (m3)
Work
Proportion
Cement (bags)
Sand     (cu m)
Agg.      (cu m)
Bricks (no.)
Rubble (cu m)
Mason (no.)
Labour (no.)
Excavation

0.00
0.00
0.00
0.00
0.00
0.18
0.15
Concreting








PCC
  1:4:8
3.00
0.46
0.84
0.00
0.00
0.09
1.77

  1:3:6
4.19
0.44
0.88
0.00
0.00
0.09
1.77

  1:2:4
6.43
0.42
0.90
0.00
0.00
0.09
1.77
Concreting








RCC
  1:4:8
3.00
0.42
0.84
0.00
0.00
0.18
2.12

  1:3:6
4.19
0.44
0.88
0.00
0.00
0.18
2.12

  1:2:4
6.43
0.42
0.90
0.00
0.00
0.18
2.12
Brick Masonary









  1:3
7.14
0.75
0.00
500.00
0.00
0.80
1.59

  1:4
5.71
0.80
0.00
500.00
0.00
0.80
1.59

  1:6
4.08
0.86
0.00
500.00
0.00
0.80
1.59
Stone Masonary









  1:5
2.40
0.42
0.00
0.00
1.25
1.06
1.77

  1:6
2.00
0.43
0.00
0.00
1.25
1.06
1.77
Plastering 12 mm









  1:3
0.13
0.01
0.00
0.00
0.00
0.08
0.08

  1:4
0.11
0.02
0.00
0.00
0.00
0.08
0.08

  1:5
0.09
0.02
0.00
0.00
0.00
0.08
0.08